EXIN PR2F Deluxe Study Guide with Online Test Engine [Q88-Q111]

Share

EXIN PR2F Deluxe Study Guide with Online Test Engine

PR2F dumps review - Professional Quiz Study Materials


For more info visit:

Exin PR2F Exam Reference

 

NEW QUESTION 88
Identify the missing words in the following sentence.
At an agreed frequency, a Team Manager will send a [ ? ] to the Project Manager.

  • A. Highlight Report
  • B. Checkpoint Report
  • C. Product Status Account
  • D. Work Package

Answer: B

 

NEW QUESTION 89
Which is a responsibility of a risk owner?

  • A. Determine project risk appetite
  • B. Own and authorize the use of the risk budget to fund risk responses
  • C. Identify risks to the project that might occur in their department
  • D. Manage, monitor and control all aspects of an assigned risk

Answer: D

 

NEW QUESTION 90
What is described as an organization's unique attitude towards risk taking

  • A. Risk management
  • B. Risk evaluation
  • C. Risk appetite
  • D. Risk tolerance

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 91
Which is a recommended quality review team role?

  • A. Project Support
  • B. Project Manager
  • C. Assurance
  • D. Administrator

Answer: D

 

NEW QUESTION 92
Which is a minimum requirement for applying the organization theme?

  • A. Each member of the project management team must have a written role description
  • B. The project manager must be appointed from the supplier organization
  • C. The frequency of communication to the project's stakeholders must be documented
  • D. The roles of the project management team must be combined, wherever possible

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Themes#Organization_Theme

 

NEW QUESTION 93
Which theme estimates the cost of delivering the project?

  • A. Change
  • B. PROGEESS
  • C. Plans
  • D. Business case

Answer: D

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Business_Case

 

NEW QUESTION 94
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

  • A. Off-specifications
  • B. Issue Register
  • C. Follow-on action recommendations
  • D. Risk Register

Answer: C

Explanation:
Section: Volume A

 

NEW QUESTION 95
Which describes a risk event?

  • A. The derivation or sources of a potential risk to the project
  • B. The sequence of events and actions that will be put in place if a risk occurs
  • C. The area of uncertainty in terms of the threat or opportunity
  • D. The achievement of a milestone on the Project Plan

Answer: C

 

NEW QUESTION 96
Which describes the 'Implement' step within the recommended risk management procedure?

  • A. Project Support will allocate the risk budget to fund the selected risk responses
  • B. The Project Manager will formulate the Risk Management Strategy
  • C. The risk owner and the risk actionee will carry out activities to control and deal with the risk
  • D. The risk owner will decide the best response to control the risk

Answer: C

 

NEW QUESTION 97
Which are advantages of a clear end to a project?
1. No further costs will be incurred by the project
2. Project products will be transferred to operations and support
3. All benefits will have been achieved
4. The project brief will be re-baselined

  • A. 2 and 3
  • B. 1 and 4
  • C. 1 and 2
  • D. 3 and 4

Answer: C

Explanation:
Explanation
Reference http://prince2.wiki/Closing_a_Project

 

NEW QUESTION 98
According to the 'continued business justification' principle, what must project benefits be aligned to?

  • A. The direction of the project board
  • B. Regular deliveries throughout the project
  • C. The business objectives
  • D. The technology available

Answer: C

Explanation:
Explanation
Reference https://www.whatisprince2.net/prince2-principle-continued-business-justification.php

 

NEW QUESTION 99
Which is an objective of the 'managing a product delivery' process?

  • A. To deliver the planned specialist products within tolerance
  • B. To ensure the business case is regularly reviewed
  • C. To assess whether the stage products have been approved
  • D. To request authorization to start the next stage

Answer: A

Explanation:
Reference http://prince2.wiki/Managing_Product_Delivery#Objective

 

NEW QUESTION 100
Which of the following statements about quality assurance and Project Assurance is true?

  • A. Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
  • B. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
  • C. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
  • D. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

Answer: B

 

NEW QUESTION 101
Where should a team manager look for information about the quality required for a product?

  • A. Project initiation documentation
  • B. Team plan
  • C. Product description
  • D. Quality management approach

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2

 

NEW QUESTION 102
Which is NOT one of the levels of plan recommended by PRINCE2?

  • A. Benefits Review Plan
  • B. Project Plan
  • C. Team Plan
  • D. Stage Plan

Answer: A

 

NEW QUESTION 103
Which describes the 'Identify Risks' step within the recommended risk management procedure?

  • A. Identify responses to risks documented in the Business Case
  • B. Gather information about the project environment and objectives
  • C. Identify uncertainties that may impact on the delivery of the project objectives
  • D. Identify the roles to be involved in risk management activities

Answer: C

 

NEW QUESTION 104
According to PRINCE2, why might there be more than one business case for a project?

  • A. There may be more than one management stage in the project
  • B. The project may be in a commercial environment with a number of suppliers
  • C. There may be more than one work package being delivered in the project
  • D. The project may be in a programme environment

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/

 

NEW QUESTION 105
What product defines the reporting requirements between the Project Manager and Team Manager?

  • A. Project Brief
  • B. Team Plan
  • C. Work Package
  • D. Product Description

Answer: C

 

NEW QUESTION 106
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

  • A. Change
  • B. Unique
  • C. Cross-functional
  • D. Risk

Answer: C

Explanation:
Topic 2, Volume B

 

NEW QUESTION 107
Which is a purpose of the 'initiating a project' process?

  • A. To provide a fixed point at which acceptance for the project product is confirmed
  • B. To produce a stage plan for each stage of a multi-stage project
  • C. To enable the project board to decide whether it is worthwhile to initiate a project
  • D. To enable an organization to understand the work needed to deliver the project's products

Answer: C

Explanation:
Section: Volume B
Explanation
Explanation/Reference:
Reference http://prince2.wiki/Initiating_a_Project#Objective

 

NEW QUESTION 108
Which is NOT a purpose of the Initiating a Project process?

  • A. Establish solid foundations for a project
  • B. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
  • C. Enable the Project Board to decide whether it is worthwhile to initiate a project
  • D. Enable a Project Board decision about the commitment of resources to a project

Answer: C

Explanation:
Section: Volume A
Explanation/Reference:

 

NEW QUESTION 109
Which is an objective of the quality review technique?

  • A. To baseline a product
  • B. To provide a common understanding of what products a project will create
  • C. To determine the quality responsibilities of a project team
  • D. To define the quality methods required within a project

Answer: A

 

NEW QUESTION 110
Which statement about risks is FALSE?

  • A. A risk is an uncertain event that, should it occur, will have an effect on a project's objectives
  • B. A risk that could have a positive impact on a project's objectives is known as an opportunity
  • C. A risk that a project's product is incomplete is known as an off-specification
  • D. A risk that could have a negative impact on a project's objectives is known as a threat

Answer: C

 

NEW QUESTION 111
......

Exam Questions Answers Braindumps PR2F Exam Dumps PDF Questions: https://passcollection.actual4labs.com/EXIN/PR2F-actual-exam-dumps.html

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 )
From Monday to Saturday

Support: Contact now