SAP c_ts4co_2021 exam is a multiple-choice test that consists of 80 questions, and the candidates have 180 minutes to complete the exam. C-TS4CO-2021 exam is available in English, Japanese, and German languages. The passing score for the SAP c_ts4co_2021 exam is 63%, and the exam fee is $550. C-TS4CO-2021 exam can be taken online or in-person at an authorized SAP testing center.

 

NEW QUESTION # 34
You want to derive the profitability segment for a line item in the universal journal using SAP S/4HANA standard configuration. What requirements must be fulfilled? Note: There are 2 correct answers to this question.

  • A. The type of the addressed ledger must be an extension ledger.
  • B. The type of the general ledger account must be primary cost/revenue or secondary cost.
  • C. Account-based Profitability Analysis must be active.
  • D. Costing-based Profitability Analysis must be active.

Answer: B,C


NEW QUESTION # 35
You would like to allocate primary and secondary costs from a cost center to another cost center. Which allocation method will you use?

  • A. Periodic reposting
  • B. Direct activity allocation
  • C. Distribution
  • D. Assessment

Answer: D


NEW QUESTION # 36
You are configuring internal order settlement. What do you define which cost element should be settled, using either the original settlement cost elements?

  • A. Settlement rule
  • B. Settlement profile
  • C. Allocation structure
  • D. Credit component (of the costing sheet)

Answer: C


NEW QUESTION # 37
How does the system derive the requirement type from the material master data? Note: There are 2 correct answers to this question.

  • A. Strategy group -> planning strategy -> requirements class -> requirements type
  • B. Strategy group -> planning strategy -> requirements type
  • C. MRP group -> requirements class -> planning strategy -> requirements type
  • D. MRP group -> Strategy group -> planning strategy -> requirements type

Answer: B,D


NEW QUESTION # 38
Which parameters are controlled by the costing type in a costing variant? Note: There are 2 correct answers to this question.

  • A. Costing sheet
  • B. Price updates
  • C. Save with date key
  • D. Price for materials

Answer: B,C


NEW QUESTION # 39
What are the prerequisites for automatic generation of the settlement rule to a market segment for a sales order item? Note: There are 2 correct answers to this question.

  • A. Profitability Analysis (CO-PA) is activated.
  • B. The sales order item is assigned to a project.
  • C. The sales order item is a cost object.
  • D. The material in the sales order item is a service.

Answer: A,B


NEW QUESTION # 40
You are running an indirect activity allocation. What do you post to the sender and receiver?

  • A. You post both quantity and cost to the receiver, and cost only to the sender.
  • B. You post both quantity and cost to the sender, and cost only to the receiver.
  • C. You post quantity and cost to both the sender and receiver.
  • D. You post only cost to both the sender and receiver.

Answer: C


NEW QUESTION # 41
You are considering using commitment management with internal orders. What do you need to do in the configuration?

  • A. Activate commitment management in both the version and the order type.
  • B. Activate commitment management in both the controlling area and the order type.
  • C. Activate commitment management in the controlling area, the order type, and in individual internal order master data.
  • D. Activate commitment management only in the controlling area.

Answer: B


NEW QUESTION # 42
You want to understand why cost are collected on sales order item level. What do you need to in the configuration? Note: There are 3 correct answers to this question.

  • A. Requirements class
  • B. Requirement type
  • C. Valuation variant
  • D. Costing type
  • E. Account assignment category

Answer: A,B,E


NEW QUESTION # 43
Which of the following steps are part of the procedure to update the standard price of the material? Note:
There are 2 correct answers to this question.

  • A. Release the cost estimate.
  • B. Archive the cost estimates.
  • C. Split the costs.
  • D. Mark the cost estimate.

Answer: A,D


NEW QUESTION # 44
Which of the following objects can be selected in templates for activity-based costing? Note: There are 2 correct answers to this question.

  • A. Business process
  • B. WBS element
  • C. Cost center/activity type
  • D. Internal order

Answer: B,D


NEW QUESTION # 45
What master data objects can you set up using time-based fields? Note: There are 2 correct answers to this question.

  • A. Activity type
  • B. Cost centers
  • C. Cost element
  • D. Statistical key figures

Answer: A,B


NEW QUESTION # 46
How can you define the overhead rate in a costing sheet? Note: There are 2 correct answers to this question.

  • A. As quantity-based surcharge
  • B. As percentage rate
  • C. As equivalence number
  • D. As lot-based surcharge

Answer: A,B


NEW QUESTION # 47
What are some of the objectives of Profitability Analysis? Note: There are 2 correct answers to this question.

  • A. Allow the company to determine standard costs and revenues according to the period accounting method.
  • B. Provide the company with a detailed view of its financial statements by areas of responsibilities.
  • C. Provide the company with information on the performance of its market segments.
  • D. Allow the company to determine if the sales force achieved their contribution margin goals.

Answer: C,D


NEW QUESTION # 48
In which module do you process profit center allocations in SAP S/4HANA?

  • A. Product cost accounting
  • B. Account-based profitability analysis
  • C. Cost center accounting
  • D. General ledger accounting

Answer: D


NEW QUESTION # 49
You want to run an assessment cycle in Profitability Analysis to allocate cost center costs during period-end closing for your organization. Which of the following objects is part of the assessment cycle?

  • A. Sender cost objects
  • B. Template
  • C. Cycle iteration
  • D. Tracing factor

Answer: D


NEW QUESTION # 50
Which of the following statements best describe Product Cost by Order? Note: There are 2 correct answers to this question.

  • A. It is used when full cost traceability is needed.
  • B. It is used when you perform repetitive manufacturing.
  • C. It is used when controlling by individual production lots or discrete quantities is needed.
  • D. It is recommended for products with a long production time.

Answer: A,C


NEW QUESTION # 51
Which of the following statements best describe Product Cost by Period? Note: There are 2 correct answers to this question.

  • A. It is used when periodic costs outweigh daily postings.
  • B. It is used when the focus of controlling is on a stable and continuous production process.
  • C. It is used to analyze work in process (WIP) based on actual costs.
  • D. It is used in conjunction with a product cost collector.

Answer: B,D


NEW QUESTION # 52
Which receiver must be allowed in the settlement profile of product cost collector?

  • A. G/L Account
  • B. Material
  • C. Order
  • D. Cost center

Answer: B


NEW QUESTION # 53
......

SAP Exam 2023 C-TS4CO-2021 Dumps Updated Questions: https://passcollection.actual4labs.com/SAP/C-TS4CO-2021-actual-exam-dumps.html

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 )
From Monday to Saturday

Support: Contact now