NEW QUESTION # 19
What document, when saved, creates a commitment for an internal order?
- A. Purchase order
- B. Production order
- C. Maintenance order
- D. Goods receipt
Answer: A
NEW QUESTION # 20
What is the timeframe of SAP SuccessFactors release cycles?
- A. Bl-annually
- B. Annually
- C. Monthly
- D. Quarterly
Answer: A
NEW QUESTION # 21
You've been tasked with converting SAP Fiori Tile groups to SAP Fiori Spaces.
Which of the following assignments should be made?
- A. Assign Tiles to Pages
- B. Assign Spaces to Pages
- C. Assign Pages to Spaces
- D. Assign Sections to Spaces
Answer: C
NEW QUESTION # 22
What information do you maintain for a general ledger account on company code level?
- A. Account currency
- B. Account group
- C. Account number
- D. Account type
Answer: A
NEW QUESTION # 23
Which backorder processing (BOP) strategy has first processing priority and is used to release confirmed stock to prioritize other orders to plan future stock needs?
- A. Gain
- B. Fill
- C. Win
- D. Lose
Answer: C
NEW QUESTION # 24
Which documents does SAP Transportation Management support when planning transportation with SAP S/4HANA? Note: There are 3 correct answers to this question.
- A. Inbound deliveries
- B. Transfer orders
- C. Returns
- D. Stock transport orders
- E. Material documents
Answer: A,C,D
NEW QUESTION # 25
What is the result of document splitting?
- A. Additional controlling documents are created
- B. Additional financial documents are created
- C. Additional logistical documents are created
- D. Additional values are created
Answer: B
NEW QUESTION # 26
When you post an accounting document, for which line item must you enter a transaction type?
- A. Customer account
- B. Asset account
- C. Material account
- D. Tax account
Answer: B
NEW QUESTION # 27
What occurs when a maintenance technician changes the status of an order to technically completed?
Note: There are 3 correct answers to this question.
- A. The orders settlement rule is executed.
- B. A time entry is posted for the maintenance technician.
- C. Open purchase requisitions are marked for deletion.
- D. Incoming invoices for the order can be processed.
- E. Reserved materials are released from the reservation.
Answer: C,D,E
Explanation:
In SAP S/4HANA Asset Management, when a maintenance technician sets an order to Technically Completed (TECO), it indicates that the physical work is finished, triggering several automatic administrative cleanup actions:
B). Material Reservations: Any materials that were reserved for the order but not used are released, making them available for other maintenance tasks or production needs.
D). Incoming Invoices: The system remains open for financial postings such as incoming invoices for external services or materials, ensuring that all actual costs can still be recorded against the order.
E). Purchase Requisitions: Any outstanding purchase requisitions associated with the order that have not yet been converted into purchase orders are automatically flagged for deletion to prevent unnecessary future procurement.
NEW QUESTION # 28
What is one advantage of using stock transport orders instead of stock transfers?
- A. The ownership transfer and carrier delivery costs are delayed until goods receipt.
- B. Goods movements occur in one step, only at goods issue.
- C. The purchase orders that are generated by MRP can be converted to stock transport orders
- D. The process of goods issue and goods receipt is monitored using the purchase order (PO) history.
Answer: D
NEW QUESTION # 29
What general ledger accounts receive postings when performing the goods receipt?
Note: There are 2 correct answers to this question.
- A. Tax Account
- B. Vendor reconciliation account
- C. Consumption account
- D. GR/IR account
Answer: C,D
NEW QUESTION # 30
When creating condition master records, what data properties does the condition type control?
Note: There are 2 correct answers to this question.
- A. Currency
- B. Sales organization
- C. Validity period
- D. Scales
Answer: C,D
NEW QUESTION # 31
Which action updates the costing-based profitability analysis?
- A. Post goods issue
- B. Post the customer's payment
- C. Save the billing document
- D. Create the outbound delivery
Answer: C
NEW QUESTION # 32
In a make-to-order process, a raw material needs to be issued from the warehouse to the manufacturing line. To which order will you post the goods issue?
- A. Stock transport order
- B. Outbound delivery order
- C. Production order
- D. Sales order
Answer: C
NEW QUESTION # 33
What is created when you post a valuated goods receipt for consumable materials?
- A. Controlling document
- B. Vendor invoice document
- C. Material ledger document
- D. Commitment
Answer: A
Explanation:
When you post a valuated goods receipt for consumable materials (materials not destined for stock but for a specific cost object), the system generates a controlling document to record the financial impact on the relevant account assignment object, such as a cost center, internal order, or project. This ensures that the costs of the consumed materials are accurately reflected in management accounting.
Why other options are incorrect
❌ A. Commitment: A commitment represents a future obligation to pay and is typically created when the purchase order is saved, not at the time of the goods receipt.
❌ B. Vendor invoice document: This document is generated during the invoice verification stage, which occurs after the goods receipt when the supplier's invoice is received and processed.
❌ C. Material ledger document: While related to material valuation and inventory management, it is not the direct result of a goods receipt for consumable materials, as these items are immediately expensed to a cost object rather than tracked as valuated stock.
NEW QUESTION # 34
......